Question: Elaydo Inc. makes flavored water and performs the following tasks in the beverage manufacturing process: Hours Receiving and transferring ingredients to storage ......... 9.0 Storing
Hours
Receiving and transferring ingredients to storage ......... 9.0
Storing ingredients .................... 270.0
Transferring the ingredients from storage ........... 4.5
Mixing and cooking the ingredients .............. 4.5
Bottling the water .................... . 3.0
Transferring the bottles to await customer shipment ...... . 9.0
a. Calculate the total cycle time of this manufacturing process.
b. Calculate the manufacturing cycle efficiency of this process.
Step by Step Solution
3.49 Rating (166 Votes )
There are 3 Steps involved in it
a Cycle time 9 270 45 45 3 9 30... View full answer