Question: Facility layout and material flowpath design are major factors in the productivity analysis of automated manufacturing systems. Facility layout is concerned with the location arrangement

Facility layout and material flowpath design are major factors in the productivity analysis of automated manufacturing systems. Facility layout is concerned with the location arrangement of machines and buffers for work-in-process. Flowpath design is concerned with the direction of manufacturing material flows (e.g., unidirectional or bidirectional; Lee, Lei, and Pinedo, Annals of Operations Research, 1997). A manufacturer of printed circuit boards is interested in evaluating two alternative existing layout and flowpath designs. The output of each design was monitored for 8 consecutive working days. The data (shown below) are saved in the file. Design 2 appears to be superior to Design 1. Do you agree? Explain fully.
Facility layout and material flowpath design are major factors in

Working Days Design 1 (units) Design 2 (units) 8/16 8/18 8/19 8/20 8/23 8/24 8/25 1,220 1,092 1,136 1,205 1,086 1,274 1.145 1.281 1,273 1,363 1,342 1,471 1.299 1,457 1,263 1,368

Step by Step Solution

3.44 Rating (157 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Let m 1 mean output for Design 1 m 2 mean output for Design 2 and m d m 1 m 2 Some preliminary calcu... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

766-M-S-H-T (4904).docx

120 KBs Word File

Students Have Also Explored These Related Statistics Questions!