Flexible Budget Required Given the data shown in the graph, what are the following: a. Budgeted fixed

Question:

Flexible Budget
Required
Given the data shown in the graph, what are the following:
a. Budgeted fixed cost per period?
b. Budgeted variable cost per unit?
c. Value of F (that is, the flexible budget for an activity level of 8,000 units)?
d. Flexible budget cost amount if the actual activity had been 16,000units?