Question: Flin Flon Construction Company is under contract to build a commercial building at a price of $4.2 million. Construction begins in January 2013 and finishes
Flin Flon Construction Company is under contract to build a commercial building at a price of $4.2 million. Construction begins in January 2013 and finishes in December 2015. Total estimated construction costs are $2.8 million. Actual construction costs incurred in each year are as follows: in 2013, $840,000; in 2014, $1,120,000; and in 2015, $840,000. Calculate the revenue and gross profit to be recognized in each year using the percentage-of-completion method.
Step by Step Solution
★★★★★
3.47 Rating (176 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Year Costs Incurred Total Estimated Cost Percentage Complete Total Revenue Rev... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
Document Format (1 attachment)
1208-B-C-A-P-C(1744).docx
120 KBs Word File