Question: For the data given in Problem 19.6, use the extended bottleneck model to develop the relationships for production rate Rp and manufacturing lead time MLT
Data given in Problem 19.6
-1.png)
The product mix fractions and station processing times for the parts are presented in the table below. The same station sequence is followed by all products: 1 ( 2 ( 3 ( 4 ( 1.
-2.png)
Station Description Number of servers Load and unload 2 human workers Process XX 3 Process Y 4 Assembly 5 Transport 1 automated server 1 automated server 2 human workers Number of carriers to be determined.
Step by Step Solution
3.40 Rating (162 Votes )
There are 3 Steps involved in it
MLT 1 50 60 685 62 160 4005 min R p 0146 pcm... View full answer