Question: Forte Company begins operations on April 1. Information from job cost sheets shows the following. Job 12 was completed in April. Job 10 was completed

Forte Company begins operations on April 1. Information from job cost sheets shows the following.

Manufacturing Costs Assigned Month Job Number June April $5,200 4,100 1,200 May

Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion.Instructions(a) What is the balance in Work in Process Inventory at the end of each month?(b) What is the balance in Finished Goods Inventory at the end of each month?(c) What is the gross profit for May, June, and July?

Manufacturing Costs Assigned Month Job Number June April $5,200 4,100 1,200 May Completed May June 10 11 12 13 14 $4,400 3,900 $3,000 April June 4,700 4,500 3,600 Not complete 4,900

Step by Step Solution

3.30 Rating (179 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Work in Process Inventory April 30 9300 10 5200 11 4100 May 31 17600 11 8000 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

54-B-M-A-J-O-C (106).docx

120 KBs Word File

Students Have Also Explored These Related Managerial Accounting Questions!