Question: Frederick Group uses ABC to account for its chrome wheel manufacturing process. Company managers have identified four manufacturing activities that incur manufacturing overhead costs: materials
Frederick Group uses ABC to account for its chrome wheel manufacturing process. Company managers have identified four manufacturing activities that incur manufacturing overhead costs: materials handling, machine setup, insertion of parts, and finishing. The budgeted activity costs for the upcoming year and their allocation bases are as follows: Activity Total
.png)
Frederick Group expects to produce 1,000 chrome wheels during the year. The wheels are expected to use 2,900 parts, require 15 setups, and consume 1,800 hours of finishing time. Job 420
Job 420 used 150 parts, required 4 setups, and consumed 120 finishing hours.
Job 510 used 500 parts, required 5 setups, and consumed 320 finishing hours.
Requirements
1.Compute the cost allocation rate for each activity.
2. Compute the manufacturing overhead cost that should be assigned to Job 420.
3. Compute overhead cost that should be assigned to Job510.
Total Budgeted Manufacturing Overhead Cost Activity Materials handling. Allocation Base Machine setup. Insertion of parts. Finishing Total. 8,700 Number of parts 4,650 Number of setups 49,300 Number of parts 75600 Finishing direct labor hours $138,250
Step by Step Solution
3.43 Rating (169 Votes )
There are 3 Steps involved in it
Req 1 Frederick Group Computation of Cost Allocation Rates Activity Total Estimated Cost Estimated Q... View full answer
Get step-by-step solutions from verified subject matter experts