Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process

Question:

Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process with a cost of $18,640 to date.
During October, Jobs 878, 879, and 880 were started. Data on costs added during October for all jobs are as follows:
Gorman Company builds internal conveyor equipment to client specifications. On

Overhead is applied to production at the rate of 80 percent of direct labor cost. Job 877 was completed on October 28, and the client was billed at cost plus 50 percent. All other jobs remained in process.

Required:
1. Prepare a brief job-order cost sheet showing the October 1 balances of all four jobs, plus the direct materials and direct labor costs during October.
2. Calculate the overhead applied during October.
3. Calculate the balance in Work in Process on October 31.
4. What is the price of Job 877?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Cornerstones of Financial and Managerial Accounting

ISBN: 978-1111879044

2nd edition

Authors: Rich, Jeff Jones, Dan Heitger, Maryanne Mowen, Don Hansen

Question Posted: