Question: Grey Company is evaluating two manufacturing process layout options, each of which has the following characteristics for producing a batch of output: Required 1. Determine
Grey Company is evaluating two manufacturing process layout options, each of which has the following characteristics for producing a batch of output:
.png)
Required
1. Determine the production (manufacturing) lead time per batch for each decision alternative.
2. Determine the process cycle efficiency (PCE) for each system.
3. Which of the two systems do you recommend? Why?
Minutes per Batch Alternative1 Alternative 2 50 20 Setup time Movement time (from start to finish) Waiting time Inspection time Processing time Total time (in minutes) 20 28 32 14 60 154 10 80 166
Step by Step Solution
3.51 Rating (174 Votes )
There are 3 Steps involved in it
Given data Minutes per Batch Activity Alternative 1 Alternative 2 Setup 50 20 Movement from start to finish 20 28 Waiting 6 32 Inspection 10 14 Proces... View full answer