Question: Guillen, Inc. began work on a $7,000,000 contract in 2014 to construct an office building. Guillen uses the completed-contract method. At December 31, 2014, the
Guillen, Inc. began work on a $7,000,000 contract in 2014 to construct an office building. Guillen uses the completed-contract method. At December 31, 2014, the balances in certain accounts were Construction in Process $1,715,000; Accounts Receivable $240,000; and Billings on Construction in Process $1,000,000. Indicate how these accounts would be reported in Guillen's December 31, 2014, balance sheet?
Step by Step Solution
3.29 Rating (155 Votes )
There are 3 Steps involved in it
Current Assets Accounts receiv... View full answer