Haig Aircraft is considering a project that has an up-front cost of $152,447 paid today at t

Question:

Haig Aircraft is considering a project that has an up-front cost of $152,447 paid today at t = 0. The project will generate positive cash flows of $60,000 a year at the end of each of the next five years. The project's NPV is $75,000 and the company's WACC is 10%. What is the project's regular payback?