Question: Handy Enterprises has gathered projected cash flows for two projects. At what interest rate would the company be indifferent between the two projects? Which project
Handy Enterprises has gathered projected cash flows for two projects. At what interest rate would the company be indifferent between the two projects? Which project is better if the required return is above this interest rate? Why?
Year _________Project I ___________Project J
0 ............... -$215,000 ................. -$215,000
1 .................. 104,000 ..................... 75,000
2 ................... 93,000 ...................... 86,000
3 .................. 79,000 ...................... 96,000
4 .................. 72,000 ..................... 105,000
Step by Step Solution
3.29 Rating (173 Votes )
There are 3 Steps involved in it
Input area Annual cash flows I J Year 0 215000 21500... View full answer