Question: Harriman Enterprises has three possible projects. Each project requires the same initial investment of $1,000,000. Harrimans chief financial officer has prepared the following cash flow
.png)
Jim Harriman, the companys president, is unsure of which project to pursue. Each holds promise for the company, but he is confused about what to do because each project generates the same amount of cash flow over the four-year period.
Required
Ignoring taxes, compute the net present value of each project at a 15 percent cost of capital. Which project should be chosen?Why?
Project X $1,250,000 ,250,000 ,250,000 ,250,000 Year Project Y Project Z $500,000 2,000,000 2,000,000 $0 4 5,000,000 500,000
Step by Step Solution
3.49 Rating (162 Votes )
There are 3 Steps involved in it
Project X is preferred because it has the highest NPV Ne... View full answer