Question: Humphrey Manufacturing is developing an activity-based costing system to improve overhead cost allocation. One of the first steps in developing the system is to classify
Humphrey Manufacturing is developing an activity-based costing system to improve overhead cost allocation. One of the first steps in developing the system is to classify the costs of performing production activities into activity cost pools.
Required
Using your knowledge of the four categories of activities, classify the cost of each activity in the following list into unit-, batch-, product-, or facility-level cost pools.

Cost Activity Cost Pool a. Engineering product design b. Supplies c. Wages of maintenance staff d. Labeling and packaging e. Plant security f. Ordering materials for a specific type of product g. Wages of workers moving units of work between work stations h. Factorywide electricity i. Salary of a manager in charge of a product line j. Sales commissions
Step by Step Solution
3.42 Rating (177 Votes )
There are 3 Steps involved in it
Cost Activity Cost Pool a Engineering product design Pro... View full answer