Question: If you have access to a commercial project management software package (Microsoft Project, for example), use it to complete a project plan based on the
If you have access to a commercial project management software package (Microsoft Project, for example), use it to complete a project plan based on the data shown in Table. Prepare a simple WBS report (or Gantt chart) showing yourwork.
.png)
Start and End Effort in Capital Dates S: 9/22 E: 9/22 Task or Subtask Expense Expense encies ice a architect 2 Purchase standard firewall 2.1 Order firewal Il Network 2.2 Order firewall Purchasing 4 4,500 8 4 Package and ship Student intern S: 10/6 6.1 Request 9 penetration test
Step by Step Solution
3.50 Rating (163 Votes )
There are 3 Steps involved in it
1 2 3 4 5 6 01 7 8 9 10 11 12 13 M AAAAAAAAAAAAA Task Name Start Contact Field Office and Co... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
241-B-A-I-S (2923).docx