Question: In 2010, Tarlo Company agrees to construct a highway for Brice County over a three-year period (2010 through 2012). The contract price is $1,200,000 and
In 2010, Tarlo Company agrees to construct a highway for Brice County over a three-year period (2010 through 2012). The contract price is $1,200,000 and the construction costs (both actual and estimated) total $705,000 for the three years. The percentage completed at the end of each year is as follows: 2010, 20%; 2011, 75%; 2012, 100%.
Required
1. Prepare a schedule showing the amount of gross profit that Tarlo Company recognizes each year using the percentage-of-completion method.
2. Prepare a schedule showing the amount of gross profit that Tarlo Company recognizes each year using the completed contract method.
Step by Step Solution
3.35 Rating (158 Votes )
There are 3 Steps involved in it
a 1200000 705000 x 20 99000 b 1200000 705000 x 75 20 27225... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
268-B-A-R-R (430).docx
120 KBs Word File