Question: In 2018, Long Construction Corporation began construction work under a three-year contract. The contract price is $1,600,000. Long recognizes revenue over time according to percentage
In 2018, Long Construction Corporation began construction work under a three-year contract. The contract price is $1,600,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2018, is as follows:
.png)
Required:
1. What was the cost of construction actually incurred in 2018?
2. How much cash was collected in 2018 on this contract?
3. What was the estimated cost to complete as of the end of 2018?
4. What was the estimated percentage of completion used to calculate revenue in 2018?
Balance Sheet Accounts receivable (from construction progress billings) $30,000 Construction in progress Less: Billings on construction contract Cost and profit of uncompleted contracts in excess of billings $100,000 (94,000) 6,000 Income Statement Income (before tax) on the contract recognized in 2018 $20,000
Step by Step Solution
3.39 Rating (155 Votes )
There are 3 Steps involved in it
Requirement 1 Construction in progress Costs incurred Profit recognized 100000 20... View full answer