In December, General Motors produced 6,600 customized vans at its plant in Detroit. The labor productivity at

Question:

In December, General Motors produced 6,600 customized vans at its plant in Detroit. The labor productivity at this plant is known to have been 0.10 vans per labor-hour during that month. 300 laborers were employed at the plant that month.
(a) How many hours did the average laborer work that month?
(b) If productivity can be increased to 0.11 vans per hour, how many hours would the average laborer work that month?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations management

ISBN: 978-0132163927

10th edition

Authors: Jay Heizer, Barry Render

Question Posted: