Job 231 was recently completed. The following data have been recorded on its job cost sheet:
Direct materials ................................$ 48,000
Direct labor-hours ............................. 610 labor-hours
Direct labor wage rate ........................ $ 13 per labor-hour
Machine-hours ................................. 350 machine-hours
Number of units completed .................. 4,500 units
The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $12 per machine-hour.
Required:
Compute the unit product cost that would appear on the job cost sheet for this job.