Question: Job 25AX required $5,000 for direct materials, $2,000 for direct labor, 200 direct labor hours, 100 machine hours, two setups, and three design changes. The
Job 25AX required $5,000 for direct materials, $2,000 for direct labor, 200 direct labor hours, 100 machine hours, two setups, and three design changes. The cost pools and overhead rates for each pool follow:
Cost Pool Overhead Rate
Assembly support $5/direct labor hour
Machining support $10/machine hour
Machine setups $250/setup
Design changes$500/design change
Determine the cost of Job 25AX.
Step by Step Solution
3.51 Rating (175 Votes )
There are 3 Steps involved in it
Direct materials 5000 Direct labor 2000 Factory ... View full answer