Johnson Electronics manufactures a power supply used in a variety of electronic, products, including printers, modems, and

Question:

Johnson Electronics manufactures a power supply used in a variety of electronic, products, including printers, modems, and routers. The demand for the part is 8,400 units per week. The production of the power supply requires six different manufacturing operations, each in sequence and each having the following processing times. The net available time to work is 70 hours per week, using two shifts.
Operation ................... Processing Time (seconds)
Operation 1 ............................... 25
Operation 2 ............................... 22
Operation 3 ............................... 30
Operation 4 ............................... 24
Operation 5 ............................... 34
Operation 6 ............................... 28
Required
1. What is the Takt time for this product?
2. Is the processing line properly balanced for this product? Why or why not?
3. What is the strategic role of Takt time, and how is it implemented by the cost management analyst?
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Cost Management A Strategic Emphasis

ISBN: 978-0077733773

7th edition

Authors: Edward Blocher, David Stout, Paul Juras, Gary Cokins

Question Posted: