Question: Lilly Inc. is using a costs-of-quality approach to evaluate design engineering efforts for a new skateboard. Lillys senior managers expect the engineering work to reduce
.png)
Requirements
1. Calculate the predicted quality cost savings from the design engineering work.
2. Lilly spent $100,000 on design engineering for the new skateboard. What is the net benefit of this €œpreventive€ quality activity?
3. What major difficulty would Lilly€™s managers have in implementing this costs-of- quality approach? What alternative approach could they use to measure quality improvement?
Predetermined Overhead Allocation Rate per Unit S 39 Predicted Reduction in Activity Units 415 415 1,000 400 225 Activity Inspection of incoming raw materials Inspection of finished goods Number of defective units discovered in-house Number of defective units discovered by customers Lost sales due to dissatisfied customers 53 70 102
Step by Step Solution
3.48 Rating (178 Votes )
There are 3 Steps involved in it
Requirement 1 Activity Predicted Reduction in Activity Units Predetermined Overhead Alloc... View full answer