Question: Livesey Company has signed a long-term contract to build a new basketball arena. The total revenue related to the contract is $120 million. Estimated costs
Livesey Company has signed a long-term contract to build a new basketball arena. The total revenue related to the contract is $120 million. Estimated costs for building the arena are $40 million in the first year and $30 million in both the second and third year. The costs cannot be reliably estimated. How much revenue should Livesey Company report in the first year under iGAAP?