Question: Lukov Incorporated provided the following data: Standard fixed overhead rate (SFOR) ............................. $5 per direct labour hour Actual fixed overhead costs ......................................... $282,686 Standard hours
Standard fixed overhead rate (SFOR) ............................. $5 per direct labour hour
Actual fixed overhead costs ......................................... $282,686
Standard hours allowed per unit ................................... 4 hours
Actual production ................................................... 14,000 un
Required:
1. Calculate the standard hours allowed for actual production.
2. Calculate the applied fixed overhead.
3. Calculate the total fixed overhead variance.
Step by Step Solution
3.42 Rating (161 Votes )
There are 3 Steps involved in it
1 Standard hours for actual units ... View full answer