Management of Mittel Rhein AG of Koln, Germany, would like to reduce the amount of time between
Question:
Management of Mittel Rhein AG of Koln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:
Inspection time .......................................................... 0.3 days
Wait time (from order to start of production) ......... 14.0 days
Process time ............................................................... 2.7 days
Move time .................................................................. 1.0 days
Queue time ................................................................. 5.0 days
Required:
1. Compute the throughput time.
2. Compute the manufacturing cycle efficiency (MCE) for the quarter.
3. What percentage of the throughput time was spent in non-value-added activities?
4. Compute the delivery cycle time.
5. If by using Lean Production all queue time during production is eliminated, what will be the new MCE?
Step by Step Answer:
Managerial Accounting
ISBN: 978-0697789938
13th Edition
Authors: Ray H. Garrison, Eric W. Noreen, Peter C. Brewer