Marc Smith's construction firm currently has three projects under way in various counties in Iowa. Each requires

Question:

Marc Smith's construction firm currently has three projects under way in various counties in Iowa. Each requires a specific supply of gravel. Three gravel pits are available in Iowa to provide for Smith's needs, but shipping costs differ from location to location. The following table summarizes the problem Smith faces. Determine the optimal shipping assignment so as to minimize totalcosts: