Question: Net Present Value It is sometimes stated that the Net Present Value approach assumes reinvestment of the intermediate cash flows at the required return. Is

Net Present Value It is sometimes stated that “the Net Present Value approach assumes reinvestment of the intermediate cash flows at the required return.” Is this claim correct? To answer, suppose you calculate the NPV of a project in the usual way. Next, suppose you do the following:

a. Calculate the future value (as of the end of the project) of all the cash flows other than the initial outlay assuming they are reinvested at the required return, producing a single future value figure for the project.

b. Calculate the NPV of the project using the single future value calculated in the previous step and the initial outlay. It is easy to verify that you will get the same NPV as in your original calculation only if you use the required return as the reinvestment rate in the previous step.

Step by Step Solution

3.44 Rating (160 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The statement is incorrect It is true that if you calculate the future value of all intermediate cas... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

29-B-C-F-C-B (14).docx

120 KBs Word File

Students Have Also Explored These Related Corporate Finance Questions!