Question: On customer orders (excluding rush orders) that require special-ordered parts, Protech Company has achieved an average lead time of 78 days, the best in its
Management plans to leave the rate of final output unchanged, reduce the average size of WIP to one-fourth of its present level, and induce vendors to reduce their total lead time by one-third.
Required:
(1) Assuming one year equals 360 days, calculate the average lead time if management's plans are implemented successfully.
(2) What advantages can be expected from the shorter lead time?
(3) What costs and other negative factors should be compared with the advantages of the shorter lead time?
Step by Step Solution
3.39 Rating (174 Votes )
There are 3 Steps involved in it
1 Protech could achieve an average lead time on these orders of 42 days calculated as follows Reduction of time in WIP 34 of present time in WIP 34 36... View full answer