On June 1, Chu Engineering, which inspects cleanup of toxic spills and waste, had two jobs in

Question:

On June 1, Chu Engineering, which inspects cleanup of toxic spills and waste, had two jobs in process with the following costs incurred to date:

On June 1, Chu Engineering, which inspects cleanup of toxic

In addition, overhead is applied to these jobs at the rate of 100 percent of direct labor costs.
As of June 1, Chu had incurred direct materials costs as shown in the table, mostly for laboratory testing materials.
During June, Chu completed both jobs and recorded them as Cost of Goods Sold.
The City of X job required no more direct materials in June, but it did require $1,200 of direct labor to complete. The Missouri River Project job required $400 of direct materials and $2,000 of direct labor to complete.
Chu started a new job, Gulf States Project, during June and put $1,600 of direct labor costs into this job and $400 of direct materials. The Gulf States Project has not been completed as of the end of June.
Provide the cost of direct materials, direct labor, and overhead (at 100 percent of direct labor cost) for the three jobs.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Managerial Accounting An Introduction to Concepts Methods and Uses

ISBN: 978-1111571269

11th edition

Authors: Michael W. Maher, Clyde P. Stickney, Roman L. Weil

Question Posted: