On June 21, 2011, Three Rivers Concrete Company signed a contract with Premier Power Incorporated to construct
Question:
Date Amount
Oct. 15, 2011……………………….. $14,280,000
Apr. 15, 2012……………………….. 6,120,000
Dec. 15, 2012……………………….. 8,160,000
Mar. 15, 2013……………………….. 7,956,000
Aug. 10, 2013……………………….. 4,284,000
Total………………………..………... $40,800,000
Estimated construction costs were as follows:
YearAmount
2011………………………………..$12,150,000
2012……………………………….. 9,450,000
2013……………………………….. 5,400,000
Total………………………………..$27,000,000
The contract was completed on September 30, 2013. Solid Concrete closes its books on December 31 each year.
Required:
Calculate the revenue, expense, and profit to be recognized in each year, using the percentage of completion method.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Financial Accounting A User Perspective
ISBN: 978-0470676608
6th Canadian Edition
Authors: Robert E Hoskin, Maureen R Fizzell, Donald C Cherry
Question Posted: