Question: Pinnacle Company's new process will be carried out in one department. The production process has an expected learning curve of 80%. Labor cost subject to
Pinnacle Company's new process will be carried out in one department. The production process has an expected learning curve of 80%. Labor cost subject to the learning effect was $60,000 for the first batch produced.
Required:
Using the learning curve, what will be the cumulative average labor cost per batch after the 16th batch has been produced?
Step by Step Solution
3.43 Rating (169 Votes )
There are 3 Steps involved in it
1 batch 60000 2 batches 480... View full answer