Presume that Litely carries a modern white kitchen ceiling lamp that is quite popular. The anticipated demand

Question:

Presume that Litely carries a modern white kitchen ceiling lamp that is quite popular. The anticipated demand during lead time can be approximated by a normal curve having a mean of 180 units and a standard deviation of 40 units. What safety stock should Litely carry to achieve a 95% service level?