Question: Refer to Problem 6-64. Develop a net material requirements plan assuming that there are currently 150 units of Part A, 40 units of Part B,
In Problem 6-64, The lead time for each of the parts in the SL72 (Problem 6-62) is one week, except for Part B, which has a lead time of two weeks. Develop a net materials requirements plan for an order of 800 SL72s. Assume that currently there are no parts in inventory.
In Problem 6-62, The Webster Manufacturing Company produces a popular type of serving cart. This product, the SL72, is made from the following parts: 1 unit of Part A, 1 unit of Part B, and 1 unit of Subassembly C. Each subassembly C is made up of 2 units of Part D, 4 units of Part E, and 2 units of Part F.
Step by Step Solution
3.33 Rating (162 Votes )
There are 3 Steps involved in it
1 2 3 4 Lead time SL72 Required Date 800 1 OnHand 0 Net 80... View full answer