Question: Refer to the original data given in Exercise III5 for Fiber Technology, Inc. The lead time required to receive an order of XL-20 is one
Refer to the original data given in Exercise III–5 for Fiber Technology, Inc. The lead time required to receive an order of XL-20 is one month.
Required:
1. Assuming stable usage of XL-20 each month, determine the reorder point for XL-20.
2. Draw a graph showing the usage, lead time, and reorder point for XL-20.
3. Suppose that monthly usage of XL-20 fluctuates between 300 and 500 canisters, although annual demand remains constant at 4,800 canisters. What level of safety stock should the materials and parts manager keep on hand for XL-20? What is the new reorder point for the chemical?
Step by Step Solution
3.41 Rating (164 Votes )
There are 3 Steps involved in it
1 The chemical XL20 should be ordered in the economic order quantity of 600 canisters when the inven... View full answer