Question: Rose is a project manager at the civil engineering consulting firm of Sands, Gravel, Concrete, and Waters, Inc. She has been collecting data on a
Rose is a project manager at the civil engineering consulting firm of Sands, Gravel, Concrete, and Waters, Inc. She has been collecting data on a project in which concrete pillars were being constructed however not all the data are available. She has been able to find out that the 10th pillar required 260 person-hours to construct, and that a 75% learning curve applied. She is interested in calculating the time required to construct the 15tand 20th pillars. Compute the values for her.
Step by Step Solution
3.41 Rating (167 Votes )
There are 3 Steps involved in it
Time for the first pillar is T10 T1 ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
7-B-E-M (69).docx
120 KBs Word File
