Question: Schmidt Co. has the following standard material and labor quantities and costs for one unit of Product SWK#468: Material ........... 1.85 pounds @ $3.50 per
Material ........... 1.85 pounds @ $3.50 per pound
Labor ........... 0.04 hours @ $12 per hour
During July, the purchasing agent found a “good deal” on the raw material needed for Product SWK#468 and bought 100,000 pounds of material at $3.15 per pound. In July, the company produced 48,000 units of Product SWK#468 with the following material and labor usage:
Material ....... 95,000 pounds
Labor ........ 2,200 hours @ $12.10 (due to a renegotiated labor contract)
a. What is the standard quantity of material and the standard labor time for July?
b. Calculate the material and labor variances for July.
c. Did the purchasing agent make a “good deal” on the raw material? Explain.
Step by Step Solution
3.47 Rating (173 Votes )
There are 3 Steps involved in it
a Standard quantity of material 48000 185 88800 pounds Standard quant... View full answer