Question: Seasons Construction is constructing an office building under contract for Cannon Company. The contract calls for progress billings and payments of $1,240,000 each quarter. The

Seasons Construction is constructing an office building under contract for Cannon Company. The contract calls for progress billings and payments of $1,240,000 each quarter. The total contract price is $14,880,000 and Seasons estimates total costs of $14,200,000. Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2014. Seasons Construction completes the remaining 25% of the building construction on December 31, 2016, as scheduled. At that time the total costs of construction are $15,000,000. What is the total amount of Revenue from Long-Term Contracts and Construction Expenses that Seasons will recognize for the year ended December 31, 2016?
Revenue ________________________Expenses:
$3,750,000...............................$ 3,750,000
$14,880,000.............................$15,000,000
$3,720,000...............................$ 3,750,000
$3,720,000...............................$ 4,200,000
Total contract price multiplied by % construction completed.

Step by Step Solution

3.47 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Revenue from longterm contract 14880000025 3720000 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1019-B-C-F-D-F(3293).docx

120 KBs Word File

Students Have Also Explored These Related Corporate Finance Questions!