Seasons Construction is constructing an office building under contract for Cannon Company. The contract calls for progress
Question:
Revenue ________________________Expenses:
$3,750,000...............................$ 3,750,000
$14,880,000.............................$15,000,000
$3,720,000...............................$ 3,750,000
$3,720,000...............................$ 4,200,000
Total contract price multiplied by % construction completed.