Seven activities have been identified as part of completing a larger project. These activities have been labeled

Question:

Seven activities have been identified as part of completing a larger project. These activities have been labeled A through G in the following table, which also displays their immediate predecessors as well as the optimistic (a), most probable (m) and pessimistic (b) expected completion times.
Seven activities have been identified as part of completing a
Seven activities have been identified as part of completing a

Calculate the expected time in weeks for each activity along with finding the critical path.