Question: Shem soft Software Technicians recently accepted a contract to develop an inventory management system for Chez and Company. Shem soft is required to complete the
.png)
Prepare the journal entries required for each year of the contract assuming Shem soft uses the percentage- of-completion method and the cost- to- cost approach for measuring progress.
Contract price 1,500,000 2015 2016 Actual construction costs incurred during the year S 255,000 800,000 Construction costs incurred in prior years Cumulative construction costs incurred to date 255,000 $1.055,000 Estimated costs to complete Estimated total costs 0 255,000 382,500 S 637500 $1.055,000 S 900,000 S600,000 $ 750,000 S 750,000 Progress bilings made during the year Cash collections during the year
Step by Step Solution
3.32 Rating (155 Votes )
There are 3 Steps involved in it
2015 2016 Actual cumulative costs incurred to date 255000 1055000 Estimated total costs 637500 10550... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
578-B-A-V-I (1581).docx
120 KBs Word File