Question: Shock Wave, Inc. began work on a $7,000,000 contract in 2008 to construct an office building. During 2008, Shock Wave, Inc. incurred costs of $1,715,000.

Shock Wave, Inc. began work on a $7,000,000 contract in 2008 to construct an office building. During 2008, Shock Wave, Inc. incurred costs of $1,715,000. At December 31, 2008, the estimated future costs to complete the project total $3,185,000. Compute the estimated revenue and gross profit to be recognized in 2008.

Step by Step Solution

3.27 Rating (159 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Revenue 1715000 ... View full answer