Question: Solve the linear programming model formulated in Problem 54 for Exeter Mines by using the computer. a. Do any of the mines have slack capacity?

Solve the linear programming model formulated in Problem 54 for Exeter Mines by using the computer.
a. Do any of the mines have slack capacity? If yes, which one(s)?
b. If Exeter Mines could increase production capacity at any one of its mines, which should it be? Why?
c. If Exeter decided to increase capacity at the mine identified in (b), how much could it increase capacity before the optimal solution point (i.e., the optimal set of variables) would change?
d. If Exeter determined that it could increase production capacity at mine 1 from 350 tons to 500 tons, at an increase in production costs to $43 per ton, should it do so?

Step by Step Solution

3.53 Rating (177 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

x 13 350 tons x 21 158333 tons x 22 296667 tons x 23 75 tons x 31 610 tons x 42 240 tons Z 77910 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

300-B-F-F-M (3287).docx

120 KBs Word File

Students Have Also Explored These Related Finance Questions!