Question: Structco Construction Company entered into a long-term construction contract at a fixed contract price of $4,900,000 on September 1, 20x4. Work has proceeded since that

Structco Construction Company entered into a long-term construction contract at a fixed contract price of $4,900,000 on September 1, 20x4. Work has proceeded since that time with the following results:
Structco Construction Company entered into a long-term construction contract at

Required:
Determine the amount of revenues, expenses, and income for 20x4, 20x5, and 20x6 by using the percentage-of-completion method.

20x4 20x5 20x6 721,000 $,190,000 Costs incurred (this year) Cost of work yet to be completed $1,715,000 (at year-end) Cash collections (this year) Year-end percent complete 3,430,000 560,000 2096 2,240,000 1,120,000 5096 525,000 1,540,000 9596

Step by Step Solution

3.40 Rating (162 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

20 x 4 20 x 5 20 x 6 Revenue 980000 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

889-B-A-A-D (381).docx

120 KBs Word File

Students Have Also Explored These Related Accounting Questions!