Bookdon plc manufactures three products, X, Y and Z, in two product cost centres: a machine shop

Question:

Bookdon plc manufactures three products, X, Y and Z, in two product cost centres: a machine shop and a fitting section; it also has two service cost centres: a canteen and a machine maintenance section. Shown below are next year?s planned production data and manufacturing cost for the business.

image

Planned overheads are as follows:

image

All machining is carried out in the machine shop. It has been estimated that approximately 70 per cent of the machine maintenance section?s cost is incurred servicing the machine shop and the remainder servicing the fitting section.

Required:(a) Calculate the following planned overhead absorption rates:1 A machine hour rate for the machine shop.2 A rate expressed as a percentage of direct wages for the fitting section.(b) Calculate the planned full cost per unit of Product X.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Accounting and Finance An Introduction

ISBN: 978-1292088297

8th edition

Authors: Peter Atrill, Eddie McLaney

Question Posted: