Question: After identifying relevant risks, the project team often employs risk-minimization techniques to lessen the probability or impact of the risk. Match the description/example of the

After identifying relevant risks, the project team often employs risk-minimization techniques to lessen the probability or impact of the risk. Match the description/example of the risk mitigation technique with the type of risk being mitigated.
1. Ensure active top management support for the project.
2. Use sensitivity analyst to consider likely alternative benefit levels.
3. Ask Microsoft to demonstrate that its software can meet the system requirements.
4. Give employees adequate incentive to use the new IT.


A. Change risk

B. Project risk

C. Technological risk

D. Solution risk

Step by Step Solution

3.48 Rating (171 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 B Project Ri... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (2 attachments)

PDF file Icon

1598_6062c74d33565_666202.pdf

180 KBs PDF File

Word file Icon

1598_6062c74d33565_666202.docx

120 KBs Word File

Students Have Also Explored These Related Accounting Information Systems Questions!