Question: Tye Company is preparing its manufacturing overhead budget for 2012. Relevant data consist of the following. Units to be produced (by quarters): 10,000, 12,000, 14,000,
Tye Company is preparing its manufacturing overhead budget for 2012. Relevant data consist of the following.
Units to be produced (by quarters): 10,000, 12,000, 14,000, 16,000.
Direct labor: Time is 1.5 hours per unit.
Variable overhead costs per direct labor hour: Indirect materials $0.70; indirect labor $1.20; and maintenance $0.50.
Fixed overhead costs per quarter: Supervisory salaries $35,000; depreciation $16,000; and maintenance $12,000.
Instructions
Prepare the manufacturing overhead budget for the year, showing quarterly data.
Step by Step Solution
3.35 Rating (173 Votes )
There are 3 Steps involved in it
Quarter 1Direct labor hours 10000 units 15 hoursunit 15000 hoursVariable overhead costs 15000 ho... View full answer