Question: Consider the revised XÌ control chart in Exercise 15-8 with ÏÌ = 0.669, UCL = 7.443, LCL = 5.125, and n = 3. Suppose that
(a) What is the probability that this shift is detected on the next sample?
(b) What is the ARL after the shift?
Exercise 15-8
The copper content of a plating bath is measured three times per day, and the results are reported in ppm. The xÌ and r values for 25 days are shown in the following table:

Day Day 1.21 1 5.45 14 7.01 1.45 0.95 1.37 5.39 15 5.83 3 6.85 1.43 16 6.35 1.04 6.74 1.29 17 6.05 0.83 5 5.83 1.35 18 7.11 1.35 7.22 1.09 0.88 19 7.32 6.39 0.92 20 5.90 1.22 8. 6.50 1.13 21 5.50 0.98 1.25 22 9. 7.15 6.32 1.21 6.55 0.76 10 5.92 1.05 23 11 6.45 0.98 24 5.90 1.20 5.95 1.19 12 5.38 1.36 25 13 6.03 0.83
Step by Step Solution
3.32 Rating (152 Votes )
There are 3 Steps involved in it
a P097 Z 503 PZ 503 PZ 097 1 016603 083397 Th... View full answer