Which of the following events will initiate a Phase 3 approval?
a.) All project deliverables have been generated, and only one or two may need additional work.
b.) There is still some scheduled work to be completed, but most of the project deliverables are performing as expected.
c.) All scheduled work has been completed, but some of the deliverables may need adjustments.
d.) All scheduled work has been completed, and all project deliverables have been generated.