The ACWP at the end of the third week for the project in Problem 11 is ($16,500)
Question:
The ACWP at the end of the third week for the project in Problem 11 is \($16,500\) Determine the CPI for the project.
Data From Problem 11:
Transcribed Image Text:
11. A project consists of six tasks. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 4. Task B is scheduled to begin at the start of Week 1 and finish at the end of Week 2. Task C is sched- uled to begin at the start of Week 3 and end at the end of Week 4. Task D is scheduled to begin at the start of Week 1 and end at the end of Week 1. Task E is sched- uled to begin at the start of Week 2 and end at the end of Week 4. Task F is scheduled to begin at the start of Week 4 and end at the end of Week 4. The budgeted cost for Task A is $10,000, for Task B is $2,000, for Task C is $3,000, for Task D is $1,000, for Task E is $6,000, and for Task F is $4,000. At the end of the third week, Task A is 80% complete, Task B is 100% complete, Task C is 40% complete, Task D is 100% complete, Task E is 55% complete, and Task F has not started. What is the SPI for the project at the end of the third week?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 100% (1 review)
Answered By
Mugdha Sisodiya
My self Mugdha Sisodiya from Chhattisgarh India. I have completed my Bachelors degree in 2015 and My Master in Commerce degree in 2016. I am having expertise in Management, Cost and Finance Accounts. Further I have completed my Chartered Accountant and working as a Professional.
Since 2012 I am providing home tutions.
3.30+
2+ Reviews
10+ Question Solved
Related Book For
Construction Accounting And Financial Management
ISBN: 9780132675055
3rd Edition
Authors: Steven J. Peterson
Question Posted:
Students also viewed these Business questions
-
Determine the total estimated cost at completion and estimated cost to complete for the project in Problem 13, assuming the CPI remains the same through the remainder of the job. Data From Problem...
-
Introduction and learning objectives When you were learning about operational analysis earlier in the term, we talked about jobs that require multiple visits to the CPU (or servers) to receive their...
-
Managing Scope Changes Case Study Scope changes on a project can occur regardless of how well the project is planned or executed. Scope changes can be the result of something that was omitted during...
-
Use the data in Exercise 13.28.To familiarize yourself with recursive least squares, estimate the savings functions for 19701981, 19701985, 19701990, and 19701995. Comment on the stability of...
-
Non-uniform displacement current figure 32-30 shows a circular region of radius R = 3.00 cm in which a displacement current id is directed out of the figure. The magnitude of the displacement current...
-
By studying, Will can produce a higher grade, GW, on an upcoming economics exam. His production function depends on the number of hours he studies marginal analysis problems, A, and the number of...
-
For the same stated rate, daily compounding is best. You would earn more "interest on interest."
-
Multiple Choice Questions The following questions deal with contingent liabilities . Choose the best response. a. The audit step most likely to reveal the existence of contingent liabilities is (1) A...
-
On July 3 1 , 2 0 1 8 , the general ledger of Hills Legal Services Inc. showed these balances: Cash $ 4 , 0 0 0 ; Accounts Receivable $ 1 , 5 0 0 ; Supplies $ 5 0 0 ; Equipment $ 5 , 0 0 0 ; Accounts...
-
Determine the total estimated cost at completion and estimated cost to complete for the project in Problem 12, assuming the CPI remains the same through the remainder of the job. Data From Problem...
-
The ACWP at the end of the second week for the project in Problem 10 is \($37,900\) Determine the CPI for the project. Data From Problem 11: 11. A project consists of six tasks. Task A is scheduled...
-
A convenience store manager earns a base salary plus small bonuses for each of ten different possible monthly milestones he meets. Typical managers can meet half of these milestones. Do they miss the...
-
Megamart provides the following information on its two investment centers. Investment Center Electronics Sporting goods Sales $ 34,200,000 16,768,000 Income $ 2,907,000 2,096,000 Average Assets $...
-
Pls give a summary use your words for Two Fed presidents resign after criticism of their investment activities .Do you agree or disagree with author's idea? Why? And what's your thought about this?...
-
Explain the roles Regulators played to support Canada through the COVID crisis. Name at least 3 regulations they implemented and/or changed. Explain how those changes have benefited customers and...
-
Loretto Outfitters is a retail chain of stores organized into two divisions (East and West) and a corporate headquarters. Corporate planners have prepared financial operating plans (budgets) for the...
-
1. Explain the conversion of energy from when the ball fully compresses the spring until the ball reaches its maximum height
-
A brass alloy is known to have a yield strength of 275MPa (40,000psi), a tensile strength of 380MPa (55,000psi), and an elastic modulus of 103GPa (15.0 10 6 psi). A cylindrical specimen of this...
-
Don Griffin worked as an accountant at a local accounting firm for five years after graduating from university. Recently, he opened his own accounting practice, which he operates as a corporation....
-
Cost-Volume-Profit Analysis at General Electric Values: Item Amount Selling Price $100,000 Variable Cost $80,000 Fixed Costs $15,000,000 Requirements: Calculate the break-even point in units....
-
Analyze the cost-volume-profit relationship for Coca-Cola. The company sells its beverage product for $2 per unit. The variable cost per unit is $1.20, and the total fixed costs are $50,000....
-
"This is really an odd situation," said Jim Carter, general manager of Highland Publishing Company. " We get most of the jobs we bid on that require a lot of press time in the Printing Department,...
Study smarter with the SolutionInn App