City Construction Company prepared their general conditions estimate based on a 20-month preliminary schedule, from mobilization through

Question:

City Construction Company prepared their general conditions estimate based on a 20-month preliminary schedule, from mobilization through receipt of a certificate of occupancy, which is a common approach. Explain why this approach is flawed – in that they might come up short in this portion of their estimate.