If you prepared an OM estimate for ACT for $100,000 on your own project and one of
Question:
If you prepared an OM estimate for ACT for $100,000 on your own project and one of the following happens on bid day, what do you do?
a. Not one subcontractor bid is received.
b. One subcontractor bid of $90,000 is received.
c. One subcontractor bid of $110,000 is received.
d. Two subcontractor bids are received, one at $50,000 and another at $95,000, or
e. Two subcontractor bids are received, one at $105,000 and one at $150,000.