If you prepared an OM estimate for ACT for $100,000 on your own project and one of

Question:

If you prepared an OM estimate for ACT for $100,000 on your own project and one of the following happens on bid day, what do you do?

a. Not one subcontractor bid is received.

b. One subcontractor bid of $90,000 is received.

c. One subcontractor bid of $110,000 is received.

d. Two subcontractor bids are received, one at $50,000 and another at $95,000, or 

e. Two subcontractor bids are received, one at $105,000 and one at $150,000.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Construction Cost Estimating

ISBN: 9780367902681

1st Edition

Authors: John E. Schaufelberger, Len Holm

Question Posted: